For a Preconstruction Termite Treatment, Termidor is applied to the soil before the final plastic sheathing is installed. The is typically, after the plumbing lines are installed, but before the plastic and either rebar or post tension cables are installed. The idea is to saturate the soil under the slab foundation before it it poured and in place. After the foundation is finished, and usually after the structure is finished, the outer foundation is then treated by digging a shallow trench along the foundation wall. Termidor is applied into the trench to create the outside barrier.